Pumping concrete requires strong attention to detail to ensure the job goes well. Not only do you need to keep your equipment in proper working order, but you also need to ensure the priming materials are going to help, not hinder the job. Unfortunately, if the priming solution is not properly mixed or applied, it can create many problems at the job site. Here are three of the most common issues concrete pump operators encounter when working with Slick-Pak concrete primers, and how to easily resolve them.

Problem: Not Enough Water in the Priming Solution

Slick-Pak requires a specific amount of water to hydrate properly and activate the lubricating agents in the material. If not enough water is used to create the Slick-Pak prime, water will be drawn from the concrete as pumped. Water pulling from the mix lowers the slump, changing the concrete’s flowability. If the primer pulls too much water from the concrete, the risk of a plug in the line increases significantly.

Solution: Use the Correct Water Dosage

Slick-Pak requires no less than 5 gallons of water for every 8 ounces of material. If you mix the material directly in the hopper, use up to 15 gallons of water per 8-ounce bag. If you are operating an extra-large boom pump, you will want to create an additional volume of material to ensure you have enough priming material. However, you should maintain the ratio of 5 gallons of water to 8 ounces of Slick–Pak.

Problem: Superplasticizers in the Concrete Mix

When a concrete mix contains a superplasticizer, priming the pump becomes even more challenging. This is because mixes containing superplasticizers tend to have less water available for the primer to absorb. So, if the priming material absorbs any water, it can increase the likelihood of a plug in the line.

Solution: Use More Water in the Primer

If you are pumping a mix that contains a superplasticizer, we recommend increasing the water ratio in the Slick-Pak priming material. Depending on the water-cement ratio in the mix and what type of superplasticizer was used, you can increase the water in the priming materials by 5 gallons per 8 ounces of material. Be sure to discuss the mix design with the engineer or quality control manager before you start creating the priming solution.

Problem: The Prime Pooled at the Bottom of the Line

When priming horizontal lines, it is not uncommon for the priming material to collect along the bottom of the line. The uneven prime can increase the water-cement ratio in part of the mix while lowering the water-cement ratio in other sections. This increases the risk of mix segregation or a plug in the line.

Solution: Use a Rubber Ball

Using a rubber ball to push the priming material through the line is a common practice that increases the efficiency of the prime. The ball forces the material to coat the line all around, creating an even coating of the material. This reduces the risk of segregation and uneven water-cement ratios in the mix as it gets pumped.

Want to Learn More?

Learn more about using Slick-Pak priming materials by checking out our technical documents. Watch the video below to see which Slick-Pak product will work best for your job. Don’t forget to follow our social media channels for more information about how our products can improve your concrete.